Politics & Government

Second Phase of Fountain Valley Sewer Improvements to Begin Monday

The next five days of the project will focus on the corner of Euclid Street and Warner Avenue.

Fountain Valley's $1.5 million sewer improvement project will continue Monday, as crews move to the corner of Euclid Street and Warner Avenue.

This phase of the project is expected to last through the end of the week, with Monday and Tuesday's work being done overnight between 9 p.m. and 6 a.m. Work during the final three days will be done from 8:30 a.m. to 4 p.m.

The entire project is scheudled to last about 95 days and repair or replace about 5,000 feet of sewer pipe at 17 total sites throughout the city, including:

Find out what's happening in Fountain Valleywith free, real-time updates from Patch.

  • Toucan/Phillips
  • Mt. Cimarron
  • Santa Alberta Circle/Ellis
  • Snowdrop
  • Bay/Talbert
  • Edinger/Brookhurst
  • Slater/Los Alamos
  • Warner/Euclid
  • Talbert—Cashew to Brookhurst
  • Magnolia/Helm
  • Newhope north of Slater
  • Whippoorwill
  • San Jose
  • Plumosa
  • Briar
  • Hudson/Edison Easement